Foundations and slabs carry everything above them, and they are buried or covered within days. Mistakes here are cheap to prevent and very expensive to fix later. These are the problems we find most often on site.
Foundations not taken to firm ground
The trench should go down to the depth and soil shown on the structural drawings, and the bottom should be firm and clean. Black cotton soil and loose fill are common on Kenyan sites and must be dealt with as the engineer specifies, not built on.
No blinding layer
A thin layer of lean concrete at the bottom of the trench gives the steel a clean, level base. Without it, steel sits in the soil and rusts.
Steel sitting on the ground, or too close to the surface
Steel needs a layer of concrete around it, called cover, to protect it from rust and fire. The cover depth is set by the engineer and is usually greater for foundations in contact with the ground than for slabs inside the building. On site, look for concrete or plastic spacer blocks holding the steel up. Steel lying flat on the ground or on the formwork has no cover.
Wrong bar sizes or wide spacing
Count the bars and measure the spacing against the drawings. Fewer, thinner or more widely spaced bars are the most common hidden saving.
Short laps
Where two bars join, they must overlap by a length set in the design. Short overlaps create weak points that cannot be seen once the concrete is poured.
Poor compaction of hardcore under ground slabs
Hardcore laid in thick layers and not compacted settles over time, and the ground slab cracks with it. It should be placed and compacted in thin layers, with a damp-proof membrane over it.
Concrete that is too wet, or not cured
Adding water makes concrete easier to place and much weaker. After pouring, concrete needs to be kept wet for several days. A slab left to dry in the Coast sun on day one will crack.
Honeycombing
Rough, gravelly patches with holes in columns and beams mean the concrete was not vibrated properly. Small patches can be repaired; large ones need an engineer's assessment.
Missing ring beams and lintels
Ring beams tie walls together and spread the roof load. They are sometimes left out to save money, and the result is cracked walls.
If you are building from abroad, ask for photos of the steel before every pour, with a tape measure in view. Better still, have an engineer inspect before the concrete goes in.