Building from abroad: 9 checks before you send the next payment

What to ask for, what to look at in photos, and when to bring in an independent engineer.

By Eng. Henry Oscar Odhiambo, PE · DEUSZ Structures

Most money lost on diaspora builds is not stolen in one go. It leaks out one instalment at a time, paid against photos and promises rather than measured work. These nine checks will not replace an engineer, but they will catch most problems early.

Before construction starts

1. Approved drawings, not just a design

Ask for the architectural and structural drawings with the county approval stamp. Structural drawings should carry the name and registration number of the engineer who designed them. A builder working from a sketch, or from "the usual way", is guessing at your foundations.

2. A contractor you can trace

Ask for the contractor's National Construction Authority (NCA) registration and check it. Ask for two previous clients you can call, and for a written contract with a price, a programme and a payment schedule.

3. A bill of quantities you understand

The BOQ lists every item of work with its quantity and rate. Without one, you have no way to tell what a payment request is actually paying for.

During construction

4. Pay for work done, not time passed

Every payment should match a stage you can verify: foundations complete, ground-floor slab cast, walls to ring beam. Hold back a retention, commonly 5 to 10 percent, until the work is finished and defects are fixed.

5. Ask for the right photos

General photos of a busy site prove little. Ask for photos before concrete is poured: the steel in the trench or on the slab, with a tape measure showing bar spacing and the spacer blocks under the steel. Once the concrete is in, nobody can see what was left out.

6. Watch for concrete pours you were not told about

A slab or column poured without warning is the most common way shortcuts get buried. Agree in writing that the contractor gives you 48 hours' notice before any pour, so the steel can be checked.

7. Check materials against the specification

Ask for delivery notes for cement and steel. Bar sizes on site should match the drawings: a Y12 bar drawn as Y16 is a weaker structure, not a saving.

When something feels wrong

8. Delays plus requests for advances

If progress slows while requests for money speed up, stop and get the work measured before paying more. This pattern comes before most stalled projects.

9. Get an independent check

An engineer who works for you, not the contractor, can measure what has really been built, compare it with what has been paid, and check the structural work before it is covered up. For most homes this costs a small fraction of a single instalment.

This guide is general advice. Every project is different; your structural engineer's drawings and instructions take priority.